Mayor Rocco Impreveduto likes to tell Holmdel residents that he and the Township Committee oppose data centers. But emails obtained by grassroots groups tell a very different story.
The emails reveal that then-Mayor Brian Foster and the Township Committee knew as early as September 2025 that a data center was being pursued at Bell Works. More troubling, rather than expressing opposition, Township officials appeared to welcome the proposal and signal their support.
Here is a timeline of some of the revealing 2025 emails:
September 8, 2025 – Bell Works’ Controller emailed Mayor Brian Foster and Township Administrator Chris Cherbini:
“The lot in the rear of Bell Works is zoned for data center (approx. footprint of the existing maintenance building), Fitness Center, and Sports and Recreation (350,000 SF). We are working with a group to develop a Data Center …”

September 11, 2025 – Somerset’s attorney emailed the Holmdel Planning Board’s planner, stating:
“…Our client has had constructive initial conversations with Township officials, and we understand those discussions have been favorable toward the data center proposal. We also understand that the Township Committee has been briefed and that feedback to date has been positive.”
This email was forwarded to Mayor Brian Foster that same day.

November 18, 2025 – In an email titled “Bell Works Holmdel Data Center” to Somerset’s attorney, Township Attorney Michael Collins wrote:
“The TC reviewed the proposal, finds that it is consistent with the redevelopment agreement, and does not have any further comments. We look forward to your client’s submission to the PB.”
Emails from 2026 further indicate that Township officials continued to be kept informed as the project advanced.
The Data Center Ban: An Extraordinary Coincidence?
Back in August, we highlighted the remarkable timing of two events: the Township Committee introduced a data center ban on July 21, 2026, and Somerset filed its Bell Works data center application just three days later—before the ban took effect.
In April 2026, a resident asked Mayor Impreveduto whether the Township could enact an ordinance banning data centers. The Mayor said it could adopt a future ordinance, but questioned whether the Township could reopen an existing redevelopment agreement, adding:
“It’s probably not the best thing to do, and I don’t see a need for that either.”
But the emails now show that the Mayor had known about the Bell Works data center proposal for more than seven months by then.
Why, knowing that this project was already in the works, did the Township wait another three months to introduce the ban? Why was the ordinance introduced only after the project could be submitted for approval and potentially grandfathered in?
These are questions Holmdel residents deserve answers to.
The Planning Board Has Grounds to Deny the Application
There is another important development.
After reviewing the application, the Holmdel Planning Board’s own consulting engineer raised serious concerns about whether the proposed data center is a permitted use under the 2012 Bell Works Redevelopment Plan. The engineer indicated that the application, as currently filed, may not comply with the plan and raised questions about the Board’s authority to review it.
In other words, the Planning Board has grounds to deny the application because the proposed use is not permitted and the Board lacks jurisdiction.
Grassroots group SHIELD’s attorney has also conducted an independent legal review and believes there are strong legal grounds to deny the application.
The Planning Board generally has 120 days to act on an application, subject to applicable extensions. Unless the applicant agrees to an extension, the deadline appears to fall on or about December 10, 2026.
Will the Planning Board Protect Holmdel?
Consider who serves on the Planning Board:
Brendan Connolley, Mayor Impreveduto’s designee, represents the Mayor.
Committeeman Gary Vanderham also serves on the Board.
Committeeman-elect TJ Mann is the current Planning Board chairman.
The remaining members were appointed by either Mayor Impreveduto or former Mayor Brian Foster over the past three years.
The Planning Board now faces an important test: Will it follow its own engineering consultant’s findings and protect Holmdel’s interests?
What Residents Can Do Now
SHIELD is asking residents to take three actions:
Sign the petition urging the Planning Board to deny the Bell Works data center application.
Attend the November 24, 2026 Township Committee meeting at 7:30 PM and make your concerns heard during public comment.
Donate to SHIELD’s legal fund to help support the legal effort. The Planning Board could begin hearing the application as early as December 1, 2026.
SHIELD has raised serious concerns about the proposed 40-megawatt data center, including 24/7 low-frequency noise, declining property values, potential health and environmental risks, and higher electricity bills.
For more information, to sign the petition, and to support SHIELD’s efforts, visit:
The question is simple: Will the Planning Board protect Holmdel’s interests and deny the Bell Works data center application?
If the application is denied, any new application would be subject to the Township’s data center ban.
Holmdel residents deserve transparency, accountability, and leadership that puts the community first.
Stay tuned.